Sunday, September 6, 2009

Contractor Bids Received

On September 3, six bids were received from general contractors. The engineer's opinion of probable cost was $2.6 million. The contractor bids were as follows:

Garney : $1.996 million

Big Valley: $2.11 million

Lillard & Clark: $2.13 million

Hydro: $2.22 million

Gould: $2.30 million

Bosco: $2.69 million