Friday, November 13, 2009

Invitation to Bid for Storage Tank Solar Reservoir Circulator

An Invitation to Bid is being advertised in the MP Times and Sky Hi Daily News on November 12 and 13. The announcement gives information about bidding for the Hot Sulphur Springs Solar Reservoir Circulator. Bids are due at the Hot Sulphur Springs Town Hall on November 23, 2009 at 11 a.m.

Beginning November 13, project specifications may be obtained for $25 at the Hot Sulphur Springs Town Hall and at the Merrick and Company offices in Aurora.

Wednesday, September 9, 2009

Contractor Bid Tabulation Spreadsheet

The contractor bids that were received on September 3, 2009 were reviewed and entered into a bid tabulation spreadsheet. Click on the spreadsheet link to see the document, the reviewed amount is entered in red.

Sunday, September 6, 2009

Contractor Bids Received

On September 3, six bids were received from general contractors. The engineer's opinion of probable cost was $2.6 million. The contractor bids were as follows:

Garney : $1.996 million

Big Valley: $2.11 million

Lillard & Clark: $2.13 million

Hydro: $2.22 million

Gould: $2.30 million

Bosco: $2.69 million

Thursday, September 3, 2009

Contractor Bid Opening - September 3, 2009

The Town Board of Hot Sulphur Springs was extremely pleased to have six general contractors submit bids for this water project. The bids ranged from $1,996,000 to $2,694,920. Garney Construction from Littleton, Colorado was the apparent low bidder. Pending review of all contractor submittals, the Town Trustees are scheduled to approve a contract award on Thursday, September 10.

Wednesday, August 19, 2009

8-18-09 Contractor Pre-Bid Meeting

A mandatory Contractor Pre-Bid Meeting was held on Tuesday, August 18. A summary of the Contractor Sign-up Sheet is available by selecting this link, CONTRACTOR MEETING SIGNUP SHEET INFORMATION.

A list of sub-contractors and suppliers interested in working on this water project is available by selecting this link, SUBCONTRACTOR AND SUPPLIER CONTACT INFORMATION SHEET.

If you would like to add your company's information to the list of sub-contractors and suppliers, please contact us at info@hotsulphurwater.com.

Construction Questions

For construction questions to be included in the Addendum(s), they must be submitted in writing, preferably by email to curtis.thompson@merrick.com.

Thursday, August 6, 2009

Invitation to Bid Announcement

An Invitation to Bid is being advertised in the MP Times and Sky Hi Daily News on August 6, 7, 13 and 14. The announcement gives information about the bid process and encourages local contractors and subcontractors to form teams to successfully bid for the project and to attend a mandatory pre-bid meeting on August 18 at the Hot Sulphur Springs Town Hall at 10 a.m.

Beginning August 12, project plans and specifications may be reviewed or purchased for $100 at the Hot Sulphur Springs Town Hall and at the Merrick and Company offices in Aurora.

A Project Summary is available online.

Friday, July 31, 2009

Mandatory Pre-bid Site Visit on August 18 at 10 a.m.

Attention Contractors and Subcontractors!

A formal Contractor Bid Advertisement will be published in the MP Times on August 6 for the ARRA Hot Sulphur Springs Water Projects. There will also be a MANDATORY pre-bid site visit held on August 18, 2009 at 10 a.m. starting at the Town Hall in Hot Sulphur Springs.

We encourage local contractors to work together to form strong bid teams. Experience with water treatment plants, lift stations, and water tanks is critical.

Subcontractors may also take the opportunity to meet and partner with other companies by attending the pre-bid site visit.

Browse the ARRA project website for more details including the PROJECT SUMMARY, to be updated regularly as more information becomes available. Preliminary plans are available in the Town Hall for review on site only and will be available for purchase.

Wednesday, July 15, 2009

Welcome Contractors

The bid process for selecting a general contractor for the water projects will begin in August. More information and a summary of bid specifications will available on this Web page soon.