Monday, June 14, 2010

Clear Well Progress

Preparation is almost complete for pouring the concrete lid to the Clear Well which will in turn form the floor for our new Water Treatment Plant. What looks like a plywood floor in the photo will hold the concrete then be removed from below after curing. Final plumbing and electrical connections through this stage will be complete and more concrete will arrive soon.

Monday, April 26, 2010

First Concrete Pour for our New Clear Well!

We completed the excavation and poured the first slab for our new clear well, which will be the tank underneath the new water treatment plant. The 20 X 10 foot slab in the photo is actually the floor for a sump. Weather permitting, we will begin to pour the walls.

Local engineering firms, TopKnot Engineering (civil engineers in Hot Sulphur Springs) and Kumar and Associates (geotechnical engineers in Fraser) are working with Garney Construction and Merrick Engineers to keep our project on track and within budget.

Material excavated from this area was transported by a local company, Harms Excavating over to Pioneer Park, where we are using the good fill material for park improvements. These improvements are being paid for with a Great Outdoors Colorado (GOCO) grant. It turns out that Pioneer Park was the closest disposal site to the water treatment plant, so our ARRA-GOCO coordination efforts continue to offer great cost benefits all around.

Monday, April 12, 2010

We have begun the 2010 construction season in earnest April 6 with the installation of “yard piping” between the new water intake vault and the existing water treatment plant which will be converted to a pre-treatment plant later this year.

The Garney crew is here in full force and will be working Monday-Thursday. Beginning Monday April 12, they will be excavating the clear well area which forms the foundation for the new water treatment plant. Excavated material will be hauled to Pioneer Park to improve camping sites and day use areas.

Wednesday, March 24, 2010

Construction begins at Both Sites

Construction for 2010 has begun at both the water treatment plant site and the water tank site. Work will be focused near the water treatment plant, until the water tank site dries out.

Tuesday, March 9, 2010

Construction to start March 15, 2010


Garney Construction’s Walt Sinclair was on the water-tank site the first week of March with Hot Sulphur Springs’ Jack Zielinski and Jim Kleeman and Bob Pfeiffer from Tim Shenk Land Surveying to look at winter access and planning locations. Sinclair will be back on site beginning March 15 with a track-excavator to perform some exploratory digging. The plan is to minimize the need for blasting rock at the tank site by excavating as much rock as possible.

Beginning April 5, a construction crew will begin more extensive excavation work at both the water tank site and water plant. Construction work will generally take place Monday through Friday between 6:30 a.m and 5 p.m.

Less explosive but as important, nonetheless, the financial/compliance team continues to hone our requisition process with the State of Colorado including new “jobs created” forms and guidance on “Buy American.” Water Project Program Manager Geoff Elliott recently visited Lisa Pine and Elisha Masters at the Colorado Department of Public Health and Environment to review the submittal process.

Saturday, February 6, 2010

Project Timeline - Feb 2010

The construction and administration teams have developed this Project Timeline for February 2010. Outdoor construction will begin soon at the water tank site. We will update this web page with more information as it is available.

Wednesday, February 3, 2010

Construction/Engineering/Accounting Meeting

Our ARRA/Stimulus team is using our scheduled winter break from construction to focus on enhancing project communications and developing final construction details. Merrick Engineers hosted a team meeting last Wednesday 25Jan10. Included were:

· Mayor Hershal Deputy and town staff Sandy White and Kerry Davidson

· Town water plant Operator Jack Zielinski and ORC John MacWilliams

· Merrick Engineers Ed Duerr, Curt Thompson, George Cicoff, and John Smart

· Garney Construction Brock Southwick, Wayne O’Brien, Maria McCracken, Solange Huggins, Walt Sinclair, and Mike Graeve

· Grand Environmental Team Karen Frey, Cindy Southway, and Geoff Elliott

Getting everyone together gave us a chance to talk about progress to date, challenges, and the best ways to press forward in 2010. We aim to begin construction as early as possible this spring.


Our morning was focused on communications including reporting, Buy American compliance, invoicing, and scheduling regular website updates and meetings. A primary goal will be to prevent team members from getting buried in e-mails while keeping things dynamic.

Our afternoon meeting dove into more details on system design. Our designated filter manufacturer Siemens/Memcor continues to improve their product, which in turn triggers a number of engineering/design adjustments. Hot Sulphur Springs is indeed getting the latest and greatest in the world of water filters!